Two planning horizons
This context spans two time horizons. They are different activities, but they share a vocabulary and a consistency boundary, so they are one bounded context rather than two.
Horizon 1 — the shift-start planning horizon
Before the shift runs, someone has to answer: given the charge due on each path and the rate we expect to run it at, how many people do we need where?
The arithmetic is trivial and the software does it:
heads = ceil(charge ÷ plannedRate)
ProposePathPlan returns that number for one path. It persists nothing. It has
no aggregate identity. Calling it twice with the same inputs is the same as
calling it once.
The commitment is not trivial and a human makes it. CommitShiftPlan
takes the full set of PathPlan lines for a site's shift and validates
them as one atomic decision:
- every line's
plannedHeadsmust be at most the path'sinstalledStations; - every line's
plannedHoursmust fit insideplannedHeads × maxHoursPerShift; - at least one line must be present.
If any line fails, none of them commit. That is why ShiftPlan is an aggregate
rather than a bag of independent path rows: the plan is only meaningful as a
whole, because heads are a finite pool being divided.
installedStations arrives in the request, rather than being looked up from
another service. Work Planning owns installed-station counts, but this context
has no dependency on Work Planning and does not want one — so the caller
carries the numbers it needs to be validated against. See
Design decisions below.
Independently of that, each line is also checked against the live installed
capacity that fulfillment-execution reports for the path's capability (the
requiredCapabilities the process-path catalogue declares for it — path
PICK is staffed at stations registered with pick). That
is a physical ceiling, and it fails loud (503) when it cannot be verified
(ADR 0014).
Horizon 2 — intra-shift assignment tracking
Once the shift is running, the plan starts drifting. Somebody calls in sick, a tote jam empties a pick aisle, the pack line starts falling behind CPT. People get moved.
Each move is recorded with AssignLabor, which:
- checks the associate holds the path's required certification;
- checks they are not currently on a logged break and their shift has not ended;
- closes any assignment that was already active (logging its hours);
- opens a new interval and raises
LaborAssigned— orLaborReassignedwhen step 3 actually closed something.
Note step 3: a second assignment does not fail, it supersedes. That matches the floor, where a supervisor moves someone without first "unassigning" them. The one-active-assignment invariant still holds absolutely — it is structural, because the aggregate holds a single optional active interval and physically cannot hold two. See ADR 0003.
Where the two horizons meet
GetStaffingGap is the join, and the only place both horizons appear at once:
plannedHeads(path) ← horizon 1, the committed ShiftPlan
activeHeads(path) ← horizon 2, the live LaborAssignments
understaffed ← activeHeads < plannedHeads
It is a projection, not stored state. No aggregate carries a "current headcount" field that could drift out of sync with the assignments it is supposed to summarise. This is the standard rule across the platform: read models are derived, never redundantly persisted on the write model.
Design decisions that fall out of this
GetStaffingGaptakessiteCodeandshiftIdas query parameters (GET /paths/{pathId}/staffing-gap?siteCode=&shiftId=;buildingIdis the deprecated alias ofsiteCode, ADR 0035) becauseShiftPlanis keyed by site plus shift. A path's planned heads are meaningless outside a specific committed plan.- A path's required certification is the certification with the same name.
Path
packrequires certificationpack. This is a naming convention, not a lookup: introducing a "path requirements" port would add a whole cross-aggregate concept for a single string comparison. The convention is documented rather than modelled. plannedHours ≤ plannedHeads × maxHoursPerShiftis how "the sum of planned hours must be valid" is enforced. A path line cannot commit more total hours than its planned heads could physically work within one shift's cap.