Flow balancing
Releasing work in the right order is not enough. Once work is on the floor, paths drift: a path staffed for 95 units/hour actually runs 70, a buffer that should hold 20 totes holds 200, an upstream path outruns a downstream one. The job of flow balancing is to detect the drift and name the correction.
Drum-Buffer-Rope, with CPT as the drum
The model is Theory-of-Constraints Drum-Buffer-Rope, mapped onto this domain:
| DBR concept | Here |
|---|---|
| Drum — the constraint that sets the pace | CPT. The truck departs when it departs; every other rate is negotiable, that one is not. |
| Buffer — protective inventory in front of the constraint | The work pool backlog on each path. |
| Rope — the signal that ties release to the drum | The release policy: admission is pulled by the drum, not pushed by whatever arrived. |
Reading it back in plain terms: work is admitted at the pace the deadline demands, buffers are watched to see whether that pace is being achieved, and when a buffer says it is not, admission upstream is throttled or capacity is moved.
Two pool types, two levers
The single most important design point: the corrective lever depends on which input you actually control.
Flow-fed pool → ThrottleUpstream
Work arrives here by physical conveyance. You cannot refuse it — the tote is already on the belt. The only lever is upstream: slow the admission that feeds this path.
Trigger: backlogDepth > alarmThreshold. Raises PathThrottled.
Release-fed pool → ReassignLabor
Here WES does control admission, and it is already exercising that control — the WIP limit is holding, which is why WIP has hit the ceiling. Throttling further would be pushing on a lever already fully pressed. Backlog is still growing, so the constraint is not admission, it is capacity: the path needs more heads.
Trigger: WIP ≥ wipLimit and backlogDepth > 0. Raises
LaborReassignmentFlagged.
Otherwise → NoActionNeeded
Silence is a legitimate output. A recommendation engine that always recommends something trains people to ignore it.
The recommendation is advice, not an action
RebalanceDecision returns a recommendation and raises an event. It does
not move headcount and does not stop the release policy. That restraint is
deliberate:
- Moving headcount belongs to
workforce-management, which owns associates, skills and shifts. This context stops at the path boundary. - Throttling is a policy change, and policy changes made automatically from a single telemetry sample are how control loops start oscillating.
So the output is a flag — a named decision with the telemetry that justified it — and a human or a downstream policy acts on it.
Why a domain service, not a scheduled job
The obvious alternative is a batch job that sweeps every path every minute and emits alerts. It was not built that way, for the same reason the reference model gives for the assignment optimiser: the logic needs a cross-aggregate, near real-time view, and it must be evaluated at the moment someone asks, not at whatever moment a scheduler last fired.
A sampled sweep has a staleness window equal to its period; a decision evaluated on read has none. And a scheduled job is untestable in the way that matters — you end up testing the scheduler instead of the rule. As a synchronous, pure decision over a pool snapshot, every branch of the rebalance table above is a two-line unit test.
See ADR-0003.
Optional labour context
The POST /paths/{pathId}/rebalance-decisions answer may include a laborPlan object: the
LaborPlanObserved projection of what Workforce Management last committed for
this path. It is additive context for the reader — the decision logic above
does not consult it. A ReassignLabor flag is far more actionable next to
"Workforce last planned 7 heads here" than on its own, but letting the number
change the decision would couple this context's flow balancing to another
context's publish cadence.