Skip to main content

Release the next highest-priority work unit on a process path

POST 

/paths/:pathId/work-releases

Applies the release policy to a process path's WorkPool — the ReleaseNextWork use case. Admits the pending work unit with the earliest (most urgent) CPT, transitioning it Pending → Released. This is continuous, priority-ordered admission (waveless), not a batch/wave release. A release-fed pool enforces its WIP limit as a hard invariant: releasing past the limit fails with 409. Publishes WorkReleased, which downstream fulfillment-execution consumes to create a Task. This is a collection-level command on the path's work pool (not scoped to a single work unit id, since the caller does not choose which unit is released — the priority policy does), analogous in REST terms to a resource-scoped bulk action.

Request​

Responses​

The released work unit, now in Released state.

Response Headers
    Idempotency-Replayed

    Present, with value true, only when this answer is a replay of a stored earlier answer for the same Idempotency-Key.