14. The delivery promise is a CPT window derived from fulfillment capability, not a configured lead time
Status
Accepted. Step A's single configured site is amended by
ADR 0047: an order carrying a
caller-assigned fulfillmentSiteId (ADR 0044) is promised against that site's CPT
schedule; DEFAULT_SITE_ID is the fallback for an order without one. Companion to process-path-management ADR 0010 (fulfillment
capability contract), accepted together, which supplies the data this
decision consumes. Depends on a future wes-work-planning ADR for
remaining capacity per CPT; this ADR is written so it degrades
correctly while that does not exist.
Context
The promise this service makes at intake is the fleet's only customer-
facing commitment, and it is the input wes-work-planning uses as the
Critical Pull Time that orders every downstream queue (WES
WorkPool.ReleaseNext and fulfillment-execution claim-next are both
earliest-CPT-first). Today that promise is computed by
order.LeadTimePolicy.PromiseDate: now plus the slowest configured
lead time among allocated lines, with lead times read from the
PROMISE_PATH_LEAD_TIMES environment variable and a 48h default. The
policy's own doc comment calls this "the honest v1 model", and it was:
there was nothing in the fleet to derive a promise from.
That is no longer true, and the gap between how this service promises and how a real fulfillment centre promises is now the largest domain- fidelity gap in the fleet:
- The promise ignores path feasibility. No signal about how long a
path takes, what it may carry, or whether it is saturated reaches
this service.
wes-work-planningpublishesBacklogThresholdBreachedandPathThrottled; nothing here consumes them. A throttled path is promised at full speed. - The promise is a timestamp, not a departure. A real promise is
"makes the 18:00 truck". Ours is "now + 24h", so WES receives a
different CPT for every order and cannot group work onto the
departure it actually competes for. Its per-CPT
ChargeForecastbuckets never coincide with the CPTs on real work units. - Path selection is a stub. ADR 0013 made
PathSelectionPolicya real domain object with one rule (PICK), explicitly deferring attribute-driven routing until real capability data existed. It now will (PPM ADR 0010). - Nothing flows back.
fulfillment-executionpublishes onlyTaskCompleted; this service's only inbound consumer is the path catalogue. A missed CPT is invisible to the order and to whoever placed it. There is no concept of re-promising. - Nothing measures it. None of on-time-to-CPT, re-promise rate, split-shipment rate or promise-to-CPT gap exists in any analytics read model.
The products this service has used as its bar (Manhattan Active OM, Salesforce OMS, a major e-commerce retailer's order platform) all treat promise calculation as first-class domain logic fed by fulfillment capability. ADR 0013 already recorded that standard; this ADR applies it to the promise itself.
Decision
1. The promise is a CPT window
Order gains a promise expressed as a value object:
Promise
cptId stable id from the site's CPTSchedule (e.g. "sp1-1800")
cutoffAt the concrete departure instant this promise targets
basis Capability | LeadTime
promiseDate (a bare time.Time) is kept on the wire and in the
database as cutoffAt for backward compatibility, and OrderAllocated
/ OrderPartiallyAllocated gain promise_cpt_id and promise_basis
as additive fields. wes-work-planning continues to build its CPT from
promise_date; once it also reads promise_cpt_id, work for the same
departure shares one CPT identity. That WES change is small and is
sequenced in the rollout below, not decided here.
2. PromisePolicy replaces LeadTimePolicy as the primary policy
A new domain service order.PromisePolicy computes the promise at
allocation time from three inputs, all supplied through outbound ports
so the domain stays free of Kafka and HTTP:
ports.ProcessPathCataloguewidened fromIsActive(pathId)to also returnCycleTimeP95andEligibilityper path (the fields PPM ADR 0010 adds; ADR 0013 explicitly left this widening for this phase).ports.CPTScheduleCache—NextCutoffs(siteId, from, n), backed by the same Kafka-fed local cache, decodingCPTScheduleChanged. (The port shipped asCPTScheduleCache, not theCPTSchedulename sketched here, to read as what it is — a cache — besideProcessPathCatalogue.)ports.PathCapacity—Remaining(pathId, cptId) (units, known bool). Until wes-work-planning publishes capacity this port has one implementation,unknown, which always reportsknown=false.
The rule, per shipment group (see §3), is a major e-commerce retailer's rule stated
plainly: the earliest cutoff that every line in the group can make.
A line can make a cutoff when (a) its path is in the cutoff's
eligiblePathIds, (b) now + cycleTimeP95 <= cutoffAt, and (c) either
remaining capacity for (path, cpt) is unknown or >= quantity. If no
cutoff within the schedule horizon qualifies, the policy returns
ErrNoFeasibleCPT and the order is placed with a LeadTime-basis
promise (below), never rejected: a building that cannot say when is
still a building that will ship.
LeadTimePolicy is kept, unchanged, as the fallback when any input is
missing: no schedule for the site, a path with no cycle time (cannot
happen after PPM's migration, but the decoder must tolerate it), or
ErrNoFeasibleCPT. Every promise records which policy produced it in
basis, so the analytics can separate real promises from fallbacks
instead of averaging them together.
3. Split shipments are promised per group, not per order
Order.AllowPartialShipment already exists (ADR 0003). Its meaning is
extended from "may release lines separately" to "may promise lines
separately": when true, lines are grouped by the cutoff they can make
and each group gets its own Promise; the order's PromiseDate()
becomes the latest of them (so no existing reader sees an earlier date
than before). When false the whole order is one group and the slowest
line governs, exactly as today. This is the checkout behaviour of
showing two dates for a book and a bag of dog food; it is a domain rule,
not a presentation choice, and it lives on the aggregate.
4. PathSelectionPolicy becomes eligibility-driven
The ADR 0013 stub is replaced by evaluation of each Active path's
declared Eligibility against the line: quantity against
maxUnitsPerLine, giftWrap, and product attributes (hazmat,
fragile) obtained through the fleet's existing product-classification
sync edge (PRODUCT_CLASSIFICATION_MODE=http|permissive, the same
pattern fulfillment-execution and wes-work-planning already use). Among
eligible paths the one with the shortest cycleTimeP95 wins. If none is
eligible, PICK remains the default (it is the only path with a
permissive eligibility after migration), so today's behaviour is the
floor, never a regression.
5. The loop closes: OrderRepromised
A new inbound Kafka consumer subscribes to
warehouse.fulfillment.events for two events fulfillment-execution will
add under its own ADR: TaskCPTMissed (a task still open past its CPT)
and PackageManifested (SLAM pass). A new use case RepromiseOrder
recomputes the promise for the affected shipment group from the current
capability/capacity inputs and, if it moves, raises
OrderRepromised{orderId, cptId_old, cptId_new, reason} on
warehouse.order-management.events and updates the aggregate. This
event is the fleet's "your delivery is delayed" trigger. It is
additive; nothing existing changes shape.
RepromiseOrder is idempotent on (orderId, sourceEventId), using the
same inbox convention the fleet's other Kafka consumers use, because
fulfillment-execution's missed-CPT sweep will re-emit on every pass.
6. Promise KPIs become part of the analytical data product
ADR 0006's Order Funnel report gains: promise basis distribution,
re-promise rate, split-shipment rate, and promise-to-cutoff gap
(cutoffAt - allocatedAt). On-time-to-CPT itself is measured where the
evidence is, in fulfillment-execution's analytics (cpt vs
manifested_at), not here. Both are exposed as read-only MCP tools per
ADR 0010 so warehouse-ops-agent can reason about promise health
without a REST detour.
Alternatives considered
- Widen
PROMISE_PATH_LEAD_TIMESand add a per-path saturation multiplier. Cheaper, but the promise stays a guess with no departure identity, and nothing can be measured against it. Rejected as the status quo with more knobs. - Let
wes-work-planningcompute the promise and reply. WES has the capacity data, but the promise is a commitment to the customer made by the order's owner; moving it downstream inverts the Customer/Supplier relationship ADR 0002 established and re-introduces the synchronous call ADR 0005 removed. Rejected. - A dedicated
delivery-orchestrationbounded context. This is the genuine production shape (a promise/sourcing engine separate from order intake), and it is where this logic goes if this service ever splits. Rejected for now because it would be a service whose only aggregate isPromise, coupled toOrderat every step; the policy is written as a pure domain service so it lifts out unchanged. - Reject orders that cannot make any CPT. A real promise engine
never refuses to sell for lack of a date; it promises later.
Rejected; the lead-time fallback with
basis=LeadTimeis the honest behaviour.
Consequences
Easier
- The promise becomes derivable from the same facts the building runs
on; when it is wrong there is a specific field (
cycleTimeP95, a schedule, a capacity signal) to correct, not an env var to widen. - Orders competing for the same truck carry the same CPT identity downstream, making WES's per-CPT charge planning and FE's earliest-CPT dispatch operate on real departures.
- Missed CPTs become a domain event this service reacts to and a KPI the ops-agent can read, instead of a silent loss.
LeadTimePolicy,AllowPartialShipmentandPathSelectionPolicyare all extended rather than replaced; their existing tests remain valid and their behaviour is the guaranteed floor.
Harder
- Two more Kafka-fed local caches (schedule, capacity) with the same startup-readiness trade-off ADR 0013 accepted: a long Kafka outage blocks startup. The alternative, serving promises from a possibly stale cache, was rejected for the same reason ADR 0013 rejected it.
- Product attributes must be looked up at intake, adding a synchronous edge to whichever context owns product classification. It is the existing fleet pattern, permissive by default, but it is a new runtime dependency on the order-intake hot path.
- The aggregate grows: multiple promises per order when partial
shipment is allowed is a real increase in
Order's state and invariants (a group may never be promised earlier than a line it contains can be released). The coverage and mutation gates oninternal/domain/orderwill need real new tests, not a threshold adjustment. - Until wes-work-planning publishes capacity, condition (c) is always
satisfied and a saturated path is still promised optimistically. The
basisfield does not distinguish "capability without capacity" from "capability with capacity"; that is deliberate to keep the enum small, and the rollout order below makes the window short. OrderRepromisedtells downstream that the promise moved but does not itself contact a customer; there is no notification context in this fleet. It is the trigger, not the email.
Rollout
Each step is its own feature branch and PR into develop, CI green
before merge, in this order:
- process-path-management ADR 0010 ships first (fields, schedule,
events). This service's
kafkacatalogdecoder is proven tolerant of the new event type and fields before that merges. - This service, step A: widen
ProcessPathCatalogue, add theCPTScheduleCacheand theunknowncapacity adapter, introducePromiseandPromisePolicy, tagbasis, additive wire fields. Behaviour change is visible only where a schedule exists. - wes-work-planning: read
promise_cpt_idwhen present; publishPathCapacityChanged(its own ADR). This service then swaps theunknowncapacity adapter for a Kafka-fed one. - This service, step B: eligibility-driven
PathSelectionPolicyand per-group promising. - fulfillment-execution:
TaskCPTMissedsweep andPackageManifestedon the outbox (its own ADR). This service, step C:RepromiseOrderconsumer andOrderRepromised. - Analytics + MCP tools + e2e-tests: two discriminating scenarios
in
e2e-tests— "a saturated path pushes the promise to the next cutoff" (same order, differentpromise_cpt_idbefore and after saturating the path) and "a task open past its CPT producesOrderRepromised". Neither can pass by accident.